Electrical Field Engineer - DOE
1 year+ supporting the DOE Uranium Processing Facility (UFP) construction at the Y-12 National Security Complex in Oak Ridge, Tennessee.
$75-90 / hr , time and a half for overtime. $100 / day per diem, mob / demob provided.
Summary :
UPF is a multi-year, multi-billion-dollar project and will be a first-of-its-kind complex for enriched uranium operations replacing a 70-year-old facility with modern buildings.
Responsibilities include ensuring assigned UPF Electrical based commodities are installed in compliance with quality standards, design specifications, nuclear codes and standards (including NFPA 70-2014).
Requirements :
- citizenship, ability to obtain a security clearance and pass drug test and background check.
- Degree in Engineering or similar from an accredited program and 6 years of experience. In lieu of degree, 12 years of related experience.
- physically able to conduct field inspections and participate in project walk-downs (extensive walking, climbing ladders and scaffolding, walking on elevated platforms or uneven surfaces, confined spaces).
of DOE, DOD, and / or commercial nuclear construction projects is required.
- Working knowledge of current design codes and standards such as NFPA 70-2014, NQA-1 requirements.
- of environmental compliance standards required on NNSA / DOE projects.
- experience as an Electrical Field Engineer.
Responsibilities :
Interface with client personnel (DOE), Plant Ops, Subcontractors.
- design documents for constructability; Material takeoffs.
- preparation / initiate requisitions for quantity listings of material and equipment.
- work packages; Ensure preparation of "as built" drawings and other job plans.
- equipment install, plan for delivery of construction materials and equipment.
- specifications, purchase orders, subcontracts, inspection reports, delivery schedules, instruction manuals, and technical data to assist and advise onsite.
- as assigned the preparation of construction estimates, cost, schedules, and budgets.
- that vendors' bids for material and / or equipment are in conformance to specifications.
- project controls documents on progress relating to cost and schedule.